Project 2013 Import Issue

The inability to deal with task progress is a big issue. Not being able to substitute the enterprise resources and instead brings the resource in as a local resource is a big issue. Then you have lost assignments in a way that causes the system to calculate new assignments to these tasks incorrectly.

Bottom line is until these fixes are address stay away from the Import Wizard.

As a workaround you could use Assign Resources dialog to replace resources that are not mapping correctly. For the task field mapping limitation, I would create a task view that exposes both resource versions and use copy and paste to transfer.